If we have already received a 36 month extension for a project, are we able to seek another extension, or is only one allowed to a maximum duration of 36 months?

Comments

1 comment

  • Comment author
    Matt H The helpers that keep the community running smoothly. UKB Community team Access Team

    Hi Tamsyn 

    Thanks for your post on the UKB Community Forum. 

    There is no limit to the number of times a project duration can be extended. The duration of a project can be extended by either 12, 24 or 36 months. 

    Please note, it is only possible to request a project duration extension once the project is in the final 12 months of its current duration. 

    Further information on submitting a duration extension request can be found here:

    https://community.ukbiobank.ac.uk/hc/en-gb/articles/23357596850333-How-do-I-extend-the-duration-of-my-project

    Many thanks 

    Matt